Paulus Engineering Uses Slide Rail System on Project in San Fernando

Paulus Engineering, Inc. Uses SBH Slide Rail System For Installation of Overflow Tank

Trench Shoring Company supported Paulus Engineering in their project to install to install a 200,000-gallon overflow storage / containment tank to help mitigate any emergency overflow issues at a juice processing plant in San Fernando. We were able to supply:

  • 72 SBH Slide Rail Panels

  • 10 Distance Pieces

  • 4 SBH MDSR Corner Posts

  • 2 SBH Slide Rail Tie Back Beams

  • 1 28’ Waster Beam

  • 1 SBH Tie Back Kit

  • 1 SBH Rigging Kit

  • 1 Standalone Davit Arm Fall Arrest / Retrieval Device

  • Miscellaneous Trench Plates

Thirteen (13) truckloads of equipment were delivered, and 12 picked up. We provided 1 Engineered Shoring Design, 5 On-Site Shoring Consultations and 1 week of Onsite Instruction From Trench Shoring Company / SBH Slide Rail Professionals.

AGC Central California
AGC San Diego
AGC Utah
Associated Subcontractors Alliance of San Diego
NAXSA
Nevada Contractors Association
NUCA Las Vegas
SCCA
Sacramento Regional Builders Exchange
United Contractors Association

Copyright © Trench Shoring Company. All rights reserved.